San Bruno Avenue & Blanken Avenue Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- San Bruno Avenue between Campbell Avenue and Dwight Street
- Blanken Avenue between Bayshore Boulevard and Candlestick Cove Way
This project will include the installation of 8" and 16" ductile iron water mains, construction of new curb ramps, and pavement restoration.
To learn more about what to expect during a water main installation project, visit sfpuc.gov/NewWaterMains
Construction Look Ahead*
Week of September 28
- Pipeline connections to the existing system:
- San Bruno Avenue between Paul and Campbell avenues
Week of October 5
- Concrete streetbase (layer below asphalt) restoration to prepare for final paving:
- San Bruno Avenue between Paul and Campbell avenues
Week of October 12
- Concrete streetbase (layer below asphalt) restoration to prepare for final paving:
- San Bruno Avenue between Paul and Campbell avenues
- Concrete street restoration:
- Intersection of Executive Park Boulevard and Candlestick Cove Way
* Dates and work subject to change