Channel Force Main Intertie
Overview
The San Francisco Public Utilities Commission (SFPUC) operates a combined sewer system that collects and treats sewage and stormwater. Our Wastewater Capital Improvement Program is upgrading and modernizing our system to ensure we can continue to protect public health and the environment now and into the future.
The Channel Force Main Intertie Project will increase the reliability, provide operational flexibility, and allow for future inspections and maintenance.
Summer 2026 Update
This year, the project progressed as crews shifted to the 48-inch bypass work connecting the 66-inch Channel Force Main to the existing Islais Creek Box Structure. Excavation efforts are currently underway on this connection work and is projected to continue through September 2026. Efforts will then shift to facility startup, testing, and utility and street restoration.
Completion of the project is anticipated at the end of 2026/early 2027.