San Bruno Avenue & Blanken Avenue Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • San Bruno Avenue between Campbell Avenue and Dwight Street
  • Blanken Avenue between Bayshore Boulevard and Candlestick Cove Way

This project will include the installation of 8" and 16" ductile iron water mains, construction of new curb ramps, and pavement restoration.

To learn more about what to expect during a water main installation project, visit sfpuc.gov/NewWaterMains


Construction Look Ahead*

Week of January 26

  • Excavate and install 16-inch and 12-inch water mains: San Bruno Avenue between Paul Avenue and Ward Street
  • Excavate connection pits: Blanken Avenue between Tunnel Avenue to Executive Park Boulevard

Week of February 2

  • Excavate and install 16-inch and 12-inch water mains: San Bruno Avenue between Paul Avenue and Ward Street
  • Excavate connection pits: Blanken Avenue between Tunnel Avenue to Nueva Avenue; San Bruno Avenue between Ward Street and Campbell Avenue
  • Water main connections: Blanken Avenue between Tunnel Avenue to Nueva Avenue

Week of February 9

  • Excavate and install 16-inch and 12-inch water mains: San Bruno Avenue between Paul Avenue and Ward Street
  • Excavate connection pits: Blanken Avenue between Executive Parkway and Gillette Avenue, and Tunnel Avenue to Nueva Avenue
  • Water main connections: Blanken Avenue between Tunnel Avenue to Nueva Avenue

 

* Dates and work subject to change

  • Construction Start: June 2025
  • Construction End: November 2026
  • Project Phase: Construction