Bay Corridor Transmission and Distribution Phase 4 and Water Improvements

Overview

The San Francisco Public Utilities Commission is extending the Bay Corridor Transmission & Distribution electrical system, upgrading aging low-pressure water infrastructure, and expanding the high-pressure Emergency Firefighting Water System to better serve the needs of existing and future customers in San Francisco’s Bayview neighborhood.


UPDATE: AUGUST 2026

Our contractor is currently installing a new water main on Cesar Chavez from Evans Avenue to Indiana Street. This work is expected to last through the end of 2026.  For information on what to expect during construction visit  sfpuc.gov/NewWaterMains

  • Construction Start: Fall 2024
  • Construction End: Winter 2026
  • Project Phase: Construction