Fulton Street Water and Sewer Improvements Project

Overview

Aging water pipelines, many of which are more than 100 years old, are being replaced to improve reliability in an area with a history of repeated water main breaks. Limited sewer rehabilitation and main installation, as well as ADA-compliant curb ramp upgrades are also planned on select blocks.  ​  

Water system upgrades are planned for:

  • Fulton Street between 31st Avenue and 36th Avenue; and 37th Avenue to Great Highway
  • 39th Avenue to 48th Avenue between Fulton and Cabrillo streets

Sewer system upgrades are planned for:

  • Fulton Street between 41st Avenue and 43rd Avenue
  • 46th Avenue between Fulton Street and Cabrillo Street

Learn more about the water main installation process at sfpuc.gov/NewWaterMains.

  • Construction Start: April 2027
  • Construction End: September 2028
  • Project Phase: Bid & Award