Laguna, Howard, and Mission Creek Outfall Rehabilitation Project
The Laguna, Howard, and Mission Creek Outfall Rehabilitation Project will rehabilitate the existing outfall structures, repair the baffles, and repair riprap located around the outfall structures. The work will not impact the discharge capability or any sewer operations.
Status: In construction
Schedule: Spring 2026 - Spring 2027
Construction Update August 2026
This contract includes three locations for outfall upgrades or rehabilitation - Laguna, Howard, and Mission Creek (3rd Street & Berry, 4th Street & Berry, and 4th Street & Channel).
- Laguna CSD Outfall - Construction began April 2026; rehabilitation work completed and awaiting final inspection.
- Howard Street Outfall - Construction anticipated to begin Late-August 2026.
- 3rd Street & Berry Street Outfall: Construction began June 2026; rehabilitation work completed and awaiting final inspection.
- 4th Street & Berry Street Outfall: Late June - Construction began June 2026, construction wrapping up.
- 4th Street & Channel Street Outfall: Construction began July 2026, construction wrapping up.
To be added to our email update list, please contact us at ssip@sfwater.org. For updates related to the Laguna Street Outfall Rehabilitation Project location specifically, please visit our webpage here.
Evans and Mariposa Outfall Improvement Project
The Evans and Mariposa Outfall Improvement Project will rehabilitate the existing outfall structures. The work will not impact the discharge capability or sewer operations.
Status: In construction
Schedule: Spring 2026 - Winter 2026
Brannan Street and Sansome Street Outfalls Improvement Project
The Brannan Street and Sansome Street Outfalls Improvement Project will rehabilitate the existing outfall structures. The work will not impact discharge capability or sewer operations.
Status: In Construction
Schedule: Spring 2026 - Fall 2026