Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of September 8

  • Excavation and installation of 8-inch and 16-inch pipeline: Douglass Street between 23rd and 24th streets

Week of September 15

  • Excavation and installation of 8-inch and 16-inch pipeline: Douglass Street between 23rd and 24th streets
  • Excavate connection pit: Elizabeth Street between Douglass and Hoffman streets

Week of September 22

  • Excavate connection pits: Diamond Street between 23rd and 26th streets; Douglass Street between 23rd and 24th streets


*Schedule subject to change

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction