Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets
  • 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of July 20

  • Concrete street restoration: 900 block of Douglass Street, near 25th Street
  • Site clean up

Week of July 27

  • Concrete street restoration: 900 block of Douglass Street, near 25th Street
  • Site clean up

As of August 3

All work has been completed, with the exception of final paving on the blocks listed below. Crews expect to complete final paving in late August to early September.

  • Douglass Street between 24th and 25th streets
  • Jersey Street between Diamond and Douglass streets
  • Diamond Street between Jersey and 26th streets
  • 25th Street between Diamond and Douglass streets


*Schedule subject to change

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction