Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of October 20
- Curb ramp installation: Intersection of Diamond Street and Elizabeth Street
- Pipeline connections: NIGHT WORK
- Intersection of Elizabeth and Hoffman streets - Wednesday, 10/22 at 7pm (This work is being done at night to accommodate the needs of neighborhood businesses which are affected by the temporary interruption of water service.)
Week of October 27
- Service changeovers: Elizabeth Street between Douglass and Hoffman streets; Douglass Street between 23rd and 25th streets
- Curb ramp installation: Intersection of Diamond Street and Elizabeth Street
Week of September November 3
- Service changeovers: Elizabeth Street between Douglass and Hoffman streets; Douglass Street between 23rd and 25th streets
- Concrete restoration of street base, curbs, and gutters: Intersection of Diamond Street and 24th Street
*Schedule subject to change