Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets
  • 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of January 12

  • Excavate and install 16-inch water main: Jersey Street between Diamond and Douglass streets
  • Excavate connection pits: Intersections of Diamond and 26th Street; and Diamond and Clipper Street
  • Concrete street base restoration: Diamond Street between 24th and Jersey streets

Week of January 19

  • Excavate and install 16-inch water main: Jersey Street between Diamond and Douglass streets

Week of January 26

  • Excavate and install 16-inch water main: Jersey Street between Diamond and Douglass streets

Week of February 2

  • Saw cut, excavate and install 16-inch water main: Douglass Street between 24th and Jersey streets
  • Curb ramp installation: Intersection of Jersey and Diamond streets
  • Excavate connection pits: Jersey Street between Diamond and Douglass streets


*Schedule subject to change

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction