 In order to complete repaving of the street after our water main construction, we will be carefully trimming select street trees, under the supervision of a certified arborist. This work will not affect the health of the trees, and will protect them from damage during paving operations.

•    North side of Elizabeth Street from Hoffman to Diamond
•    West side of Diamond from 23rd to Jersey
•    West side of Douglass from 23rd to Elizabeth
•    North side of Jersey from Diamond to Castro

When: April 20-21, 2026
* Weather and/or construction issues may postpone this work

Map showing North side of Elizabeth Street from Hoffman to Diamond •	West side of Diamond from 23rd to Jersey •	West side of Douglass from 23rd to Elizabeth •	North side of Jersey from Diamond to Castro

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets
  • 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of April 13

  • Excavate and install 8-inch water main: Douglass Street between 24th and 25th streets
  • Sawcut, excavate, and install 8-inch water main: 25th Street between Douglass and Diamond streets (The date for this work has been moved earlier than originally anticipated.)

Week of April 20

  • Excavate and install 8-inch water main: 25th Street between Douglass and Diamond streets (The date for this work has been moved earlier than originally anticipated.)
  • Excavate connection pits: Douglass Street between 24th and Jersey streets
  • Final street paving:
    • Jersey Street between Castro and Diamond streets
    • Diamond Street between Jersey and 23rd streets
    • Elizabeth Street between Diamond and Hoffman streets
    • Douglass Street between 23rd and 24th streets

Week of April 27

  • Excavate and install 16-inch water main: Douglass Street between 24th and 25th streets
  • Excavate connection pits: Jersey between Diamond and Douglass streets


*Schedule subject to change

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction