Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of September 8
- Excavation and installation of 8-inch and 16-inch pipeline: Douglass Street between 23rd and 24th streets
Week of September 15
- Excavation and installation of 8-inch and 16-inch pipeline: Douglass Street between 23rd and 24th streets
- Excavate connection pit: Elizabeth Street between Douglass and Hoffman streets
Week of September 22
- Excavate connection pits: Diamond Street between 23rd and 26th streets; Douglass Street between 23rd and 24th streets
*Schedule subject to change