Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of August 18
- Service changeovers: Diamond Street between 25thand 26th streets
- Locate underground utilities (potholing): Douglass Street between 23rd and 25th streets
Week of August 25
- Installation of 8-inch pipeline: Elizabeth Street between Douglass and Hoffman streets
Week of September 1
- Installation of 8-inch pipeline: Elizabeth Street between Douglass and Hoffman streets; Douglass Street between 24th and 25th streets