Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
- 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of January 12
- Excavate and install 16-inch water main: Jersey Street between Diamond and Douglass streets
- Excavate connection pits: Intersections of Diamond and 26th Street; and Diamond and Clipper Street
- Concrete street base restoration: Diamond Street between 24th and Jersey streets
Week of January 19
- Excavate and install 16-inch water main: Jersey Street between Diamond and Douglass streets
Week of January 26
- Excavate and install 16-inch water main: Jersey Street between Diamond and Douglass streets
Week of February 2
- Saw cut, excavate and install 16-inch water main: Douglass Street between 24th and Jersey streets
- Curb ramp installation: Intersection of Jersey and Diamond streets
- Excavate connection pits: Jersey Street between Diamond and Douglass streets
*Schedule subject to change