Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of June 2
- Excavate and install 8" water pipeline: Diamond Street between 25th and 26th streets
- Pipeline connections: Intersection of Jersey and Noe streets; and Jersey Street near Castro Street
- Nightwork: Tuesday, June 3 from 9pm - 1am (This work is being done at night to accommodate the needs of neighborhood businesses which are affected by the temporary interruption of water service.)
Week of June 9
- Excavate and install 8" water pipeline: Diamond Street between 25th and 26th streets
- Pothole to locate underground utilities: Douglass Street between 23rd and 25th streets
Week of June 16
- Excavate and install 8" water pipeline: Diamond Street between 25th and 26th streets
*Schedule subject to change