Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets
  • 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of May 11

  • Excavate connection pits: Douglass Street between 24th and 25th streets
  • Service changeovers: Douglass Street between 24th and 25th streets
  • Curb ramp installation: Intersection of 25th and Diamond streets
  • Pipeline connections: 
    • Jersey Street between Diamond and Douglass streets
    • Intersection of 24th and Douglass streets - NIGHT WORK on May 12 from 9pm - 1am 
      (This work is being performed at night to accommodate the needs of neighborhood businesses which are affected by the temporary interruption of water service.)

Week of May 18

  • Service changeovers: Douglass Street between 24th and 25th streets
  • Curb ramp installation: Intersection of 25th and Diamond streets
  • Pipeline connections: Douglass Street between 24th and 25th streets

Week of May 25

  • Service changeovers: Douglass Street between 24th and 25th streets


*Schedule subject to change

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction