Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets
  • 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of February 2

  • Excavate and install 16-inch water main: Douglass Street across 23rd Street and 24th Street intersections
  • Curb ramp installation: Intersection of Jersey and Diamond streets

Week of February 9

  • Excavate and install 16-inch water main: Douglass Street across 24th Street intersection and through to Jersey Street
  • Curb ramp installation: Intersection of Jersey and Diamond streets

Week of February 16

  • Excavate and install 16-inch water main: Douglass Street across 24th Street intersection and through to Jersey Street


*Schedule subject to change

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction