Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of June 23
- Excavate and install 8" and 16" water pipeline: Diamond Street between 25th and 26th streets
Week of June 30
- Excavate and install 8" and 16" water pipeline: Diamond Street between 25th and 26th streets
- Service changeovers: Diamond Street between 23rd and 25th streets
Week of July 7
- Service changeovers: Diamond Street between 23rd and 25th streets
- Curb ramp installation: Intersection of Jersey and Sanchez streets
*Schedule subject to change