Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of May 5
- Excavate and 8" water pipeline installation: Diamond Street between 23rd and 25th streets
- Excavate and perform service changeovers: Jersey Street between Noe and Castro street
Week of May 12
- Excavate and 8" water pipeline installation: Diamond Street between 23rd and 26th streets
- Excavate and perform service changeovers: Jersey Street between Noe and Castro street
Week of May 19
- Excavate and 8" water pipeline installation: Diamond Street between 25th and 26th streets
*Schedule subject to change