Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of June 23

  • Excavate and install 8" and 16" water pipeline: Diamond Street between 25th and 26th streets


Week of June 30

  • Excavate and install 8" and 16" water pipeline: Diamond Street between 25th and 26th streets
  • Service changeovers: Diamond Street between 23rd and 25th streets


Week of July 7

  • Service changeovers: Diamond Street between 23rd and 25th streets
  • Curb ramp installation: Intersection of Jersey and Sanchez streets


*Schedule subject to change

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction