Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
- 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of February 2
- Excavate and install 16-inch water main: Douglass Street across 23rd Street and 24th Street intersections
- Curb ramp installation: Intersection of Jersey and Diamond streets
Week of February 9
- Excavate and install 16-inch water main: Douglass Street across 24th Street intersection and through to Jersey Street
- Curb ramp installation: Intersection of Jersey and Diamond streets
Week of February 16
- Excavate and install 16-inch water main: Douglass Street across 24th Street intersection and through to Jersey Street
*Schedule subject to change