East SOMA Sewer Improvements Project
Overview
The East SOMA Sewer Improvements Project will rehabilitate the existing 100-year-old sewer mains and sewer lower laterals located under several streets highlighted on the Project Maps.
Please check this project page for timely updates about the construction schedule and upcoming locations. To receive these updates via email, please complete the form on the right-hand side of this page.
Construction Scheduled for Late April – Early May 2025
Mission Street (7th and 6th)
- Excavation and replacement of sewer laterals and culverts will be continuous in the area from April 21 –25 and April 28 – May 2.
- Excavation of sewer culverts and other sewer related upgrades will continue May 5 - May 9.
Mission Street (6th and 5th)
- Excavation and replacement of sewer laterals will occur on April 25 and continue from April 28 – 29.
Howard Street (Fremont and Main)
- De-energization on street will occur May 1.
- Excavation of large manhole will occur on May 2 and continue May 5 – 7.
- Excavation and replacement of sewer laterals will occur May 8 – 9.
Schedule Subject to Change, last updated on 04/23/2025. Have questions? Please reach out to us by email at ssip@sfwater.org with 'East SOMA' in the subject line.