2-Week Construction Look-Ahead Schedule:
Week of March 16
- Howard Street (8th Street to 9th Street)
March 16-20: Installation of manhole.
March 18-19: Replacing sewer laterals. - 8th Street (Harrison Street to Bryant Street)
March 20: Installation of manhole.
Week of March 23
- Howard Street (8th Street to 9th Street)
March 23 - 24: Installation of manhole, cont. - 8th Street (Harrison Street to Bryant Street)
March 23 - 27: Installation of manhole, cont.
*Please note that construction schedule is subject to change, for questions or concerns please email us at ssip@sfwater.org with West SOMA in the title.
What to Expect During Construction:
- SEWER SERVICE: These services will NOT be interrupted during construction.
- PARKING: Street parking will be impacted near construction zones. No-Parking signs will be posted 72 hours in advance.
- TRAFFIC: Partial lane closures may be necessary to ensure safety of workers and the public. Advance notice and detour signage will be provided, as needed.
- MUNI: Passenger loading zone for bus stops may be temporarily relocated. Advance notice and detour signage will be provided as needed.
- ACCESS: Follow posted signage on site. Driveway access to businesses and residents in the work zone will be maintained during construction.
- NOISE: Neighbors may hear construction noise periodically. Noisy work will be conducted in compliance with the San Francisco Noise Ordinance.
- ODORS: If necessary, odor control measures will be in place during construction.
- NOTICE: A 30-day and 10-day notice will be distributed prior to construction to residents and businesses within the project area before construction begins.