December 2025 Construction Schedule: *
Divisadero Street (Fell Street to Oak Street)
- December 1 – 5, 2025: Installation of sewer main and manholes will occur in the area.
- December 8 – 12, 2025: Replacement of sewer laterals and other sewer-related upgrades will occur in the area.
- December 15, 2025: Inspection of sewer main via CCTV will occur in the area.
- December 15 – 19, 2025: Curb ramp restoration will occur in the area.
Fells Street (Cole Street to Clayton Street)
- December 1 – 2, 2025: Lining of sewer laterals will occur in the area.
7th Avenue (Judah Street to Lawton Street)
- December 3 – 5, 2025: Lining of sewer laterals will occur in the area.
Mission Street (11th Street to 8th Street)
- December 8 – 9, 2025: Inspection of sewer laterals will occur in the area.
Natoma Street (9th Street to 8th Street)
- December 10, 2025: Inspection of sewer laterals will occur in the area.
Howard Street (9th Street to 8th Street)
- December 11, 2025: Inspection of sewer laterals will occur in the area.
9th Street (Mission Street to Folsom Street)
- December 12, 2025: Inspection of sewer laterals will occur in the area.
8th Street (Harrison Street to Bryant Street)
- December 15, 2025: Inspection of sewer laterals will occur in the area.
*Please note that construction schedule is subject to change, for questions or concerns please email us at ssip@sfwater.org with ‘West SOMA’ in the title.
What to Expect During Construction:
- SEWER SERVICE: These services will NOT be interrupted during construction.
- PARKING: Street parking will be impacted near construction zones. “No-parking” signs will be posted 72 hours in advance.
- TRAFFIC: Partial lane closures may be necessary to ensure safety of workers and the public. Advance notice and detour signage will be provided, as needed.
- MUNI: Passenger loading zone for bus stops may be temporarily relocated. Advance notice and detour signage will be provided as needed.
- ACCESS: Follow posted signage on site. Driveway access to businesses and residents in the work zone will be maintained during construction.
- NOISE: Neighbors may hear construction noise periodically. Noisy work will be conducted in compliance with the San Francisco Noise Ordinance.
- ODORS: If necessary, odor control measures will be in place during construction. Please see CIPP page for more information: sfpuc.org/curedpipe.
- NOTICE: A 30-day and 10-day notice will be distributed prior to construction to residents and businesses within the project area before construction begins.