3-Week Construction Look-Ahead Schedule:
Week of Jan. 26, 2026:
- Divisadero Street (Fell Street to Oak Street)
Jan. 29: Street restoration. - Fells Street (Cole Street to Clayton Street)
Jan. 26: Replace sewer laterals.
Jan. 27: Street restoration. - Cole and Oak Street Intersection
Jan. 27: Street restoration. - 7th Avenue (Judah Street to Lawton Street)
Jan. 28 – 30: Installation of manhole.
Week of Feb. 02, 2026:
- Fells Street (Cole Street to Clayton Street)
Feb. 06 – 08: Sewer main lining. - 7th Avenue (Judah Street to Lawton Street)
Feb. 02 – 06: Installation of manhole, continued.
Week of Feb. 09, 2026:
- Fells Street (Cole Street to Clayton Street)
Feb. 13 – 15: Sewer main lining. - 7th Avenue (Judah Street to Lawton Street)
Feb. 09 – 13: Installation of manhole, continued. - Panhandle Scope (See Project Map)
Feb. 09 – 13: Sewer main lining.
*Please note that construction schedule is subject to change, for questions or concerns please email us at ssip@sfwater.org with West SOMA in the title.
What to Expect During Construction:
- SEWER SERVICE: These services will NOT be interrupted during construction.
- PARKING: Street parking will be impacted near construction zones. No-Parking signs will be posted 72 hours in advance.
- TRAFFIC: Partial lane closures may be necessary to ensure safety of workers and the public. Advance notice and detour signage will be provided, as needed.
- MUNI: Passenger loading zone for bus stops may be temporarily relocated. Advance notice and detour signage will be provided as needed.
- ACCESS: Follow posted signage on site. Driveway access to businesses and residents in the work zone will be maintained during construction.
- NOISE: Neighbors may hear construction noise periodically. Noisy work will be conducted in compliance with the San Francisco Noise Ordinance.
- ODORS: If necessary, odor control measures will be in place during construction.
- NOTICE: A 30-day and 10-day notice will be distributed prior to construction to residents and businesses within the project area before construction begins.