*3-Week Construction Look-Ahead Schedule:
9th Street (Mission Street to Folsom Street)
Stanyan Street (Fulton Street to Hayes Street)
- September 25 to 26: Post-CCTV
Stanyan and Carl Street Intersection
Divisadero and Oak Street Intersection
Natoma Street (8th Street to 9th Street)
- Sept. 28 – Sept. 30: Backfilling manhole
Mission Street (11th Street to 8th Street)
- Sept. 28 – Sept.30: Line sewer main
- Sept. 30 – Oct. 2: Backfill manhole
- October 2: Abandon manhole
Howard Street (8th Street to 9th Street)
8th Street (Harrison Street to Bryant Street)
*Please note that construction schedule is subject to change, for questions or concerns please email us at ssip@sfwater.org with West SoMa in the title.
What to Expect During Construction:
- SEWER SERVICE: These services will NOT be interrupted during construction.
- PARKING: Street parking will be impacted near construction zones. No-Parking signs will be posted 72 hours in advance.
- TRAFFIC: Partial lane closures may be necessary to ensure safety of workers and the public. Advance notice and detour signage will be provided, as needed.
- MUNI: Passenger loading zone for bus stops may be temporarily relocated. Advance notice and detour signage will be provided as needed.
- ACCESS: Follow posted signage on site. Driveway access to businesses and residents in the work zone will be maintained during construction.
- NOISE: Neighbors may hear construction noise periodically. Noisy work will be conducted in compliance with the San Francisco Noise Ordinance.
- ODORS: If necessary, odor control measures will be in place during construction.
- NOTICE: A 30-day and 10-day notice will be distributed prior to construction to residents and businesses within the project area before construction begins.