*3-Week Construction Look-Ahead Schedule:
Mission Street (11th St. to 8th St.)
- June 22 - 26: Sewer cleaning and pre-CCTV
- June 29 - July 2: Install manhole
9th Street (Mission Street to Folsom Street)
- June 15 - 18: Replace sewer laterals and culverts
- June 19: Install manhole and riser
- June 22 - 23: Install manhole and riser
- June 22 - 26: Replace sewer laterals and culverts
*Please note that construction schedule is subject to change, for questions or concerns please email us at ssip@sfwater.org with West SoMa in the title.
What to Expect During Construction:
- SEWER SERVICE: These services will NOT be interrupted during construction.
- PARKING: Street parking will be impacted near construction zones. No-Parking signs will be posted 72 hours in advance.
- TRAFFIC: Partial lane closures may be necessary to ensure safety of workers and the public. Advance notice and detour signage will be provided, as needed.
- MUNI: Passenger loading zone for bus stops may be temporarily relocated. Advance notice and detour signage will be provided as needed.
- ACCESS: Follow posted signage on site. Driveway access to businesses and residents in the work zone will be maintained during construction.
- NOISE: Neighbors may hear construction noise periodically. Noisy work will be conducted in compliance with the San Francisco Noise Ordinance.
- ODORS: If necessary, odor control measures will be in place during construction.
- NOTICE: A 30-day and 10-day notice will be distributed prior to construction to residents and businesses within the project area before construction begins.