Geary Boulevard Sewer and Water Improvements Phase 2

Aging water and sewer pipelines are being replaced or rehabilitated on Geary Boulevard between 32nd Avenue and Stanyan Street. Most of this infrastructure is over 120 years old, dating back to the late-1800’s when it was installed for the early development of the Richmond District. 

Sewer upgrades will improve system reliability, increase capacity, and reduce the risk of flooding and backups for residents and businesses. Water system upgrades will improve water pressure, flow and reliability for homes, businesses, and firefighting. Approximately 1.4 miles of sewer mains and 6.7 miles of water mains will be replaced or rehabilitated.  

The project is split into two segments - Segment A: 32nd Avenue to 12th Avenue; Segment B: 12th Avenue to Stanyan Street.


As of June 2026: The project is currently 80% complete. Work in Segment A is mostly finished with only one small section of sewer work and restoration remaining between 31st and 32nd Avenue. All other work in Segment A is fully completed. 

In Segment B, all of the sewer, water, and fiber installation has been completed. Crews are currently focusing on water main connections and restoration of the parking strips, curbs, gutters, and roadways. 

See the lookahead schedule in the tab below for where crews will be working.