Westside Pump Station Reliability Improvements Project

Overview

Construction Update – Summer 2026: Upgrades continue at the Westside Pump Station this summer, with completion anticipated in summer 2027. The traffic detour will continue until the end of major construction activities.

The Westside Pump Station (WSS) is an all-weather facility that pumps the sanitary and stormwater flow from the West side of the City to the Oceanside Treatment Plant. The WSS and associated facilities have been in service for numerous decades in the harsh marine environment. The aging mechanical and electrical infrastructure must operate daily to maintain water quality requirements.

  • Construction Start: Spring 2021
  • Construction End: Summer 2027
  • Project Phase: Construction