Stormwater Management Requirements

New: Non-Compliance Fees and Fines

On May 12, 2026, the San Francisco Public Utilities Commission adopted a schedule of fees and fines to better ensure customer compliance with the Stormwater Management Ordinance (SMO), specifically its mandated inspection and maintenance requirements. The schedule of fees and fines becomes effective on July 1, 2026.

These fees and fines are intended to promote compliance and cover the costs of additional staff time if needed. Our team is eager to work with the small number of non-compliant properties to bring them into compliance and avoid fees and fines. Our goal is for all properties to come into compliance by the October start of the 2026-27 rainy season. For any questions regarding your property, please contact our team at stormwaterinspections@sfwater.org.

A general timeline of enforcement actions is as follows:

  • Annual Self-Certification (ASC) notifications will be sent in September. Property owners have one month to submit their ASC. Those who do not submit will receive a certified letter in October, warning of delinquency and providing information about the $500.00 Non-Reporting Fee that will be assessed. A complimentary 30-day period will be granted to comply with the requirement from the post date. If the ASC is not received within those 30 days, the non-reporting fee will be issued in November.
  • SMO re-inspection fees will be applicable in September. These fees may be required during the SMO Triennial Inspections and will apply only after the initial inspection. The amount will depend on the compliance order issued. If a property is determined to need minor corrections, only photo verification will be necessary (no fee applies); other properties pending larger correction issues may require a re-inspection to confirm the corrections have been made adequately. Each re-inspection will incur a fee ($677 for the first, $1,353 for the second, $2,030 for the third).
  • Properties that are non-responsive to mandatory Triennial inspection requests, found to be out of compliance with the SMO, and unwilling to make necessary corrections to achieve compliance will be liable for an Administrative Penalty Order, assessed at $1,111/day for each acre out of compliance with the SMO. For those properties, notices of violation will be sent in September. Administrative Civil Penalty Orders will be sent 30 days later in October. The fine will be issued 30 days later in November.

For more information about the fees and fines and how they are calculated, please see pages 3-4 of the Commission resolution. The 2026-27 Rates Schedule and Fees for Water and Sewer Service will be available here.

Program Information and Resources

The Stormwater Management Requirements and Design Guidelines (SMR) outlines the mandatory requirements for managing post-construction stormwater runoff and provides guidance on how to incorporate green infrastructure into site design. The performance requirements vary depending on the type of sewer system servicing a project (combined or separate), the agency with jurisdiction over the project (SFPUC or Port), and the size of the project. Refer to the SMR Summary Flyer for more information.

The Stormwater Management Ordinance (SMO) – Public Works Code, Article 4.2 Sections 147-147.6 – requires compliance with the SMR. It applies to all new and redevelopment projects that create and/or replace 5,000 square feet or more of impervious surface in combined sewer areas or 2,500 square feet or more in separate sewer areas.

Contact: StormwaterReview@sfwater.org

By complying with the Stormwater Management Ordinance, you will be eligible to apply for a stormwater credit to lower your monthly sewer bill. Find out more at https://stormwater.sfpuc.org/.

SCP APPROVAL PROCESS: Interface with DBI Permitting

*NEW* SCP Project Review and Approval Process – September 2025

DBI Site Permit with Addenda

  • Preliminary SCP (PSCP) shall be reviewed for ‘intake acceptance’ by SFPUC prior to DBI Site Permit submittal.
  • Final SCP (FSCP) shall be reviewed for ‘intake acceptance’ by SFPUC prior to DBI Architectural Addenda submittal.
  • FSCP shall be approved prior to DBI Certificate of Final Completion (CFC) issuance.

DBI Full Building Permit 

  • PSCP shall be approved by SFPUC and FSCP shall be submitted to SFPUC for ‘intake acceptance’ prior to DBI Full Permit submittal.
  • FSCP shall be approved prior to DBI Certificate of Final Completion (CFC) issuance.

SCP PREPARATION, APPROVALS, AND INSPECTION UPDATES

Submittal Guidance

SCP Materials

Managing stormwater, which may otherwise wash pollutants into our waterways or overwhelm our sewer system, is critical to protecting water quality, wildlife, and public health. Like many California municipal agencies, the SFPUC administers a stormwater management program developed in accordance with the Clean Water Act. Effective May 22, 2010 and updated in 2016, the San Francisco Stormwater Management Ordinance (SMO) requires new and redevelopment projects to manage stormwater using green infrastructure (i.e. stormwater controls or best management practices) and to maintain that green infrastructure for the lifetime of the project.

SMO requirements apply to:

Large Projects: New and redevelopment projects (or subdivisions) that create and/or replace ≥5,000 square feet of impervious surface in the separate and combined sewer areas, and

Small Projects: New and redevelopment projects that create and/or replace 2,500-5,000 square feet of impervious surface in separate sewer areas.

Activities that create or replace impervious surface include, but are not limited to, the construction or alteration of any building or structure and the creation or replacement of outdoor impervious surfaces such as parking areas, driveways, or private street areas.

The SMO does not apply to certain activities such as:

  • Pavement maintenance activities such as top-layer asphalt grinding and repaving within the existing footprint;
  • Replacement of existing sidewalks and streets dedicated to and accepted by the City;
  • Interior remodeling projects;
  • Re-roofing; or
  • Utility repair work requiring trenching or excavation with in-kind surface replacement.