Warnerville Substation Rehabilitation

Overview

The Warnerville Substation facilities have reached the end of their working life and are in need of rehabilitation.  This project was divided into two subprojects. Subproject A – Warnerville Substation Rehabilitation Phase 1 is complete.  Subproject B – Warnerville Substation Rehabilitation Phase 2 is currently in construction. 

  • Construction Start: Phase I March 2024, Phase 2: May 2026
  • Construction End: Summer 2027
  • Cost: $24.3 million
  • Project Phase: Construction