Large Landscape Grant

We are currently accepting applications for the SFPUC's Large Landscape Grant Program (LLGP). If you have questions about the LLGP process, or if you don't have a specific water-saving project identified at this time, but think there are water-saving improvements that you could implement in the next five years, please contact us at landscape@sfwater.org.

The LLGP provides retail water service customers funding for projects that result in significant and permanent reduction in potable water use for landscape irrigation.

Grant funding is limited to no more than $4.00 per square foot of the eligible project area and requires a 50 percent match. The SFPUC will evaluate and select projects for grant award based on how well they meet the eligibility criteria set forth in the Program Rules and on availability of funds.

The SFPUC may require repayment of grant funds for projects not completed within two years or as otherwise extended by mutual agreement, and for projects that do not achieve the projected water savings within two years of project installation or plant establishment.


Review the Program Terms & Conditions


 

LLGP Program Steps:

Step 1 

Applicant submits an application including, but not limited to, a project work plan, Project Area measurements, schedule, budget, water saving calculations based on the most recent 3-year baseline consumption, and a site map of the proposed area currently being watered by the irrigation system.

Step 2 

SFPUC reviews application to determine if additional information is required to confirm eligibility and to schedule a mandatory inspection for sites with multiple meters.

  • If eligibility requirements are met, funding is available, and the program is still open, the SFPUC issues Applicant a Reservation Letter, indicating that funds will be reserved for the Applicant’s proposed project for nine (9) months
  • If eligibility requirements are not met, the SFPUC issues Applicant a Rejection Letter, indicating the project does not meet criteria and will not be awarded funds

Step 3 

Applicants that receive a Reservation Letter complete the following within nine (9) months from the date of the letter:

  • (For Landscape Water Efficiency Projects only): Complete and submit a landscape documentation package, including irrigation, planting, and grading plans; water use calculations confirming the water savings of the project based on the most recent 3-year average baseline consumption of potable water for irrigation, and a soil management report. Additional landscape documentation package information can be found at: Grants | SFPUC
  • If non-City property, complete and execute a Grant Agreement with the SFPUC, using a Grant Agreement template provided by the SFPUC. If City property, complete and execute a MOU with the SFPUC. Upon execution of the Grant Agreement, Grantees must also:
    • Provide a valid copy of an insurance policy declaration that names the City and County of San Francisco, the San Francisco Public Utilities Commission, its board members and commissions, and all authorized agents and representatives, and members, directors, officers, trustees, agents, and employees as additional insureds
    • Comply with insurance requirements and mandates by the City and County of San Francisco, inclusive of commercial general liability and workers compensation
    • Obtain a valid Bidder and Supplier member with the City and County of San Francisco for Grantees who are not City of San Francisco departments

All Applicants must ensure their contractor(s) will pay prevailing wage for construction of the project unless the LLP funds a private residential project or is less than $1,000.00

Step 4 

SFPUC reviews the landscape retrofit plan and if approved, coordinates with Applicant to develop and execute a Grant Agreement that also indicates the schedule for grant fund disbursement; upon execution of the Grant Agreement, the Applicant becomes a Grantee.

Step 5 

Grantee completes installation of project within two years of receiving the first disbursement of funds from the SFPUC, pursuant to the terms of their Agreement/MOU and all terms for payment, funding, taxes and insurance noted in these Terms and Conditions.

Step 6 

Grantee maintains all new retrofit equipment and components and/or replaces dead plantings paid for through SFPUC funds during the full duration of the Agreement/MOU term. Grantee also maintains the completed project in a water-efficient manner that meets the stated water-saving goals and remains in place through the full duration of the Grant Agreement term. Any removal or failure to maintain equipment and plantings during the Agreement/MOU term is subject to repayment to the SFPUC.