Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
- 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of May 4
- Excavate and install 16-inch water main: Douglass Street between 24th and 25th streets
- Excavate connection pits: Douglass Street between 24th and 25th streets
- Replace brick cistern: Intersection of Elizabeth and Douglass streets
- Pipeline connections: Jersey Street between Diamond and Douglass streets
Week of May 11
- Service changeovers: Douglass Street between 24th and 25th streets
- Curb ramp installation: Intersection of 25th and Diamond streets
- Pipeline connections: Jersey Street between Diamond and Douglass streets; Douglass Street between 24th and 25th streets
Week of May 18
- Service changeovers: Douglass Street between 24th and 25th streets
- Curb ramp installation: Intersection of 25th and Diamond streets
- Pipeline connections: Douglass Street between 24th and 25th streets
*Schedule subject to change