Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of May 5

  • Excavate and 8" water pipeline installation: Diamond Street between 23rd and 25th streets
  • Excavate and perform service changeovers: Jersey Street between Noe and Castro street


Week of May 12

  • Excavate and 8" water pipeline installation: Diamond Street between 23rd and 26th streets
  • Excavate and perform service changeovers: Jersey Street between Noe and Castro street


Week of May 19

  • Excavate and 8" water pipeline installation: Diamond Street between 25th and 26th streets


*Schedule subject to change

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction