San Bruno Avenue & Blanken Avenue Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • San Bruno Avenue between Campbell Avenue and Dwight Street
  • Blanken Avenue between Bayshore Boulevard and Candlestick Cove Way

This project will include the installation of 8" and 16" ductile iron water mains, construction of new curb ramps, and pavement restoration.

To learn more about what to expect during a water main installation project, visit sfpuc.gov/NewWaterMains


Construction Look Ahead*

Week of August 4

  • Locate underground utilities (potholing): Blanken Avenue between Tunnel Avenue and Candlestick Cove Way

Week of August 11

  • Locate underground utilities (potholing): San Bruno Avenue between Campbell Avenue and Dwight Street

Week of August 18

  • Locate underground utilities (potholing): San Bruno Avenue between Campbell Avenue and Dwight Street

 

* Dates and work subject to change

  • Construction Start: June 2025
  • Construction End: November 2026
  • Project Phase: Construction