September 2025
Preparation of meadow to receive new sod

July 2025
Installation of mats and topsoil is complete, openings are being created for planting of new vegetation

June 2025
Placement of mats to stabilize soil

Installation of irrigation system on slope

May 2025
Final grading of slope

Finished slope prior to vegetation restoration

April 2025
Contractor's final work on the upper part of the slope

March 2025
Our removal of hazard trees in Pine Lake Park is complete.

Improving drainage on the western end of Pine Lake Park

Slope restoration continues

February 2025
Retaining wall mid-way up the slope (will not be visible when project is complete)

Soil compaction

January 2025
Building up the slope

Progress on the lower end of the slope

December 2024
Retaining wall construction

Slope protection during atmospheric river rain event

Preparing slope for installation of steel beams
Steel beams after installation on slope

Cement poured above retaining wall

November 2024
Restoration of soil on slope, and materials being prepared for the retaining wall

October 2024
Overview of work area and dog park

Machinery used to remove debris from the soil so that it may be reused


Filtering debris to provide clean material for re-use on the slope repair, October 9, 2024

Work area prior to "grubbing of slope", September 30, 2024

Covering the slope with temporary waterproofing, March 22, 2024

View of washout area and debris field, March 14, 2024

Washout area, March 12, 2024

The day of the valve failure, March 8, 2024