Sewer Upgrades in San Francisco

For Today, Tomorrow and Decades to Come

We strive to minimize disruption and to provide our neighbors with timely and accurate status updates. Public notices have been mailed to the work areas listed.
If you are experiencing a water, power, or sewer emergency service issue call our 24-hour hotline at 3-1-1 or log on at sf311.org.

A reliable system requires maintenance. SFPUC-led infrastructure projects partner with many agencies to "dig once" and work efficiently. However, coordination challenges and/or unforeseen complications (e.g. unstable soil conditions) may result in delays. A pause in work occurs between sewer upgrade inspections and street restoration.

Thank you for your patience as we upgrade our critical infrastructure to be resilient and reliable. For more information, contact us at: ssip@sfwater.org or 415-554-3233.

Can't find any information about the work on your street? see Contacts and Resources below.


Construction is listed by Street | Project Number | Supervisoral District Number

5th Avenue (Judah to Irving streets) | WW-725 | D7
Sewer upgrades inspections in progress, estimated completion June.

6th Avenue (Geary Blvd. to Anza St.) | WW-725 | D1
Sewer upgrades complete, road restoration pending, estimated completion June.

14th Avenue (Fulton to Anza streets) | WW-725 | D1
Sewer upgrades inspections in progress, estimated completion June.

16th Avenue (Lincoln Way to Irving St) | WW-725 | D7
Sewer upgrades inspections in progress, estimated completion June.

20th Street (Mission to San Carlos streets) | WW-729 | D9
Sewer upgrades anticipated to begin early June, estimated duration 1 month.

30th Street (Noe to Harper streets.) | WWW-725 | D8
Sewer upgrades anticipated to begin TBD

38th Avenue (Cabrillo to Balboa streets.) | WWW-726 | D1
Sewer upgrades in progress, estimated completion June.

Bay Street (Hyde to Larkin streets) | WW-709 | D2
Sewer upgrades complete, road restoration pending, estimated to be completed early July. Delayed due to poor soil conditions.

Bay Street (Leavenworth to Hyde streets) | WW-709 | D2
Delayed due to poor soil conditions. Crews to complete Hyde to Larkin streets, then will return to this section of Bay St.
Project is 44% complete: Project is estimated to be completed June through early August.

Buchanan Street (Sutter to Bush streets.) | WWW-725 | D5
Sewer upgrades complete, road restoration pending, estimated completion end of June.

California Street (Walnut to Laurel streets) | WW-725 | D2
Sewer upgrades complete, road restoration pending, estimated completion end of June.

Chestnut Street (Columbus Ave. to Mason St.) | WW-725 | D1
Sewer upgrades anticipated to begin TBD

Columbus Avenue (Beach to North Point streets) | WW-709 | D2
Sewer upgrades anticipated to begin late June, estimated duration 4 months.

Dolores Street (San Jose Ave. to Day St.) | WWW-725 | D8
Sewer upgrades anticipated to begin TBD

Jackson Street (Gough to Octavia streets) | WW-725 | D2
Sewer upgrades complete, road restoration pending, estimated completion end of June.

Marina Boulevard & Yacht Road | WW-709 | D2
Sewer upgrades 68% Complete. Paused at this time due to poor soil conditions, anticipated to resume late September, estimated duration 2 months.

Oakwood Street (18th to 19th streets) | WW-729 | D8
Sewer upgrades anticipated to begin early July, estimated duration 1 month.

Park Street (Leese St. to Holly Park Cir.) | WW-725 | D9
Sewer upgrades in progress May through July, estimated duration 1.5 months.

Pixley Street (Webster to Buchanan streets) | WW-720 | D2
Sewer upgrades in progress April through July, estimated duration 3 months.

Post Street (Franklin St. to Van Ness Ave.) | WW-725 | D2
Sewer upgrades in progress May through June, estimated duration 1 month.

Starr King Way & Franklin Street | WW-725 | D2
Sewer upgrades in progress May through June, estimated duration 1 month.

Winston Drive & Stonecrest Drive Easement | WW-725 | D7
Sewer upgrades anticipated to begin TBD, delayed due to utility investigation, estimated duration 1.5 months.