CONSTRUCTION LOOK AHEAD -- ASPHALT PAVING CLEAN-UP
Week of August 3-7 -- The major portion of the work of grinding down and replacing the asphalt paving on portions of 6th Avenue, Locksley Avenue, Warren Drive, Lawton Street, and Aloha Street for the Parnassus Project was finished August 6.
There will be minor project activities August 7: setting manhole covers (after paving), temporary striping and general
clean-up.
Week of August 10-14 -- Minor project activities continue this week but without traffic control. These activities include: setting manhole covers (after paving), temporary striping, and general clean-up for the project.
A punch list developed by the contractor and SFPUC staff on a walk-through inspection of all aspects of the construction will also be corrected. The streets that were excavated to install new sections of ductile iron water pipelines will have their asphalt surfaces restored.
Weather and construction issues could impact the schedule.
General workdays and hours (weather permitting) are Monday – Friday, 7:00 a.m. to 5:00 p.m.