Active Alerts

If you are experiencing a water, power, or sewer emergency or service problem call our 24-hour hotline at 3-1-1 or (415) 701-2311 from outside SF or log on at sf311.org. Learn more or review active service alerts.

Construction at the Southeast Treatment Plant

Overview

Built in 1952, the Southeast Treatment Plant is the City’s largest wastewater treatment facility, handling nearly 80% of San Francisco's combined stormwater and wastewater every year. However, many of its facilities are past their useful life and generate odors that impact the neighborhood.

The SFPUC is currently investing over $3 billion in critical upgrades to transform this facility into a modern resource recovery center. By doing so, we will continue to protect our communities and environment while creating an attractive workplace and neighborhood asset that serves the entire City for decades to come.

As we continue to make progress with our infrastructure investments, we are proud to be providing jobs and contracting opportunities to local residents and businesses. When complete, the plant will work better, look better, and smell better for the neighborhood, our staff, and the entire City!

CONSTRUCTION UPDATES (Late Fall 2025)

Demolition of Old Headworks Building Nears Completion

The final scope of the New Headworks Facility Project is nearing its completion. Earlier this year, crews began demolition of last portion of the old headworks on the northwest side of the Southeast Treatment Plant. This 150-million-gallons per day (MGD) wastewater facility was deemed redundant with the successful completion and activation of the new 250 MGD headworks that began operations in Summer 2024 and has already processed billions of gallons of combined wastewater since opening. Demolition of this decommissioned facility has been ongoing this summer and is still expected to be completed by late Fall 2025.

Learn more about the New Headworks Project, including impacts expected during demolition at sfpuc.gov/headworks.

New Digester Painting Continues

Part of the aesthetic upgrades to five new digesters at the Southeast Treatment Plant is now visible as crews on the Biosolids Digester Facilities Project continue painting the exterior of each digester in a colorful new pattern! The color scheme - a selection of muted blues and greens - is meant to evoke the wastewater cleaning process. Crews have already started to prime the 60-feet digesters and work to paint each one began in late July and will continue through late Fall 2025. The newly painted digesters will be particularly visible to commuters passing the west side of the treatment plant on Caltrain and drivers on the I-280 overpass.

Learn more about the Biosolids Digesters Facilities Project online at sfpuc.gov/digesters

Construction to Begin in Late Fall 2025 on New Operations, Engineering, and Maintenance Buildings at the Corner of Phelps Street and Jerrold Avenue

In late Fall 2025, construction will start on two new buildings that will provide much-needed shop space for maintenance and trade crews as well as workspaces and facilities for operation, engineering, and maintenance staff. The buildings will also be the SFPUC and City of San Francisco's first Mass Timber buildings. Construction is expected to last roughly two years. These critical upgrades are part of where your ratepayer dollars go to ensure our system continues to protect public health and the environment. 

While the contractor is required to abide by the City's noise and vibration ordinances, neighbors should expect some noise and limited dust during this work. The project team will work to minimize disruption to normal neighborhood activity. 

Learn more about the New Operations, Engineering, and Maintenance Buildings Project online at sfpuc.gov/sepbuildings.

Biosolids' Biogas Utilization Project

The Biogas Utilization Project is a key component of the Biosolids Digester Facilities Project, designed to transform how biogas—a byproduct of wastewater treatment—is managed and reused. Instead of using biogas for on-site energy generation as originally planned, the SFPUC will upgrade it to pipeline quality renewable natural gas for injection into PG&E’s natural gas pipeline.

Duration: construction on this project will begin in January 2026 with an anticipated completion date of early 2027.

Questions? Contact our team by calling our hotline at (415) 551-4SEP (4737) or email ssip@sfwater.org.

  • Construction Start: 2018