Hampshire and York Streets Utility Upgrade Project
Overview
Critical upgrades to our aging water and sewer infrastructure are planned for:
- Hampshire and York streets between Mariposa and Cesar Chavez streets
- Bryant Street between Precita Avenue and 26th Street
- 23rd and 25th streets between Hampshire Street and Potrero Avenue
- 26th Street between Bryant and Hampshire streets
- Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp
This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration.
Construction Look Ahead
Week of October 7th
- Work on catch basins and culverts - Intersection of 26th and Hampshire Street
- Excavate pits and perform service changeovers - Hampshire Street between Cesar Chavez and 25th streets; 26th Street between York and Hampshire streets
Week of October 14th
- Excavate and water pipeline installation - 23rd Street between Hampshire Street and Potrero Avenue
- Excavate pits and perform service changeovers - 25th Street between Hampshire Street and Potrero Avenue; Hampshire Street between Cesar Chavez and 25th streets; 26th Street between York and Hampshire streets
- Streetbase and pavement restoration - Hampshire Street between 24th and 25th streets
Week of October 21st
- Excavate and water pipeline installation - Hampshire Street between 18th and Mariposa streets
- Excavate pits and perform service changeovers - 25th Street between Hampshire Street and Potrero Avenue; Hampshire Street between Cesar Chavez and 25th streets; 26th Street between York and Hampshire streets