Hampshire and York Streets Utility Upgrade Project
Overview
Critical upgrades to our aging water and sewer infrastructure are planned for:
- Hampshire and York streets between Mariposa and Cesar Chavez streets
- Bryant Street between Precita Avenue and 26th Street
- 23rd and 25th streets between Hampshire Street and Potrero Avenue
- 26th Street between Bryant and Hampshire streets
- Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp
This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration.
Construction Look Ahead
Week of June 9
- Final paving - Hampshire Street between 18th and 24th streets; 23rd Street between Hampshire Street and Potrero Avenue; and 26th Street between Hampshire and Bryant streets
- Monday, June 9: Street grinding on Hampshire Street between 18th and 21st streets; Minimal impacts to driveway access.
- Tuesday, June 10: Asphalt repaving on Hampshire Street between 18th and 20th streets; Streets temporarily closed 7am - 5pm
- Wednesday, June 11: Street grinding on Hampshire Street between 21st and 24th streets; 23rd Street between Hampshire Street and Potrero Avenue; and 26th Street between Hampshire and Bryant streets; Minimal impacts to driveway access.
- Thursday, June 12: Asphalt repaving on Hampshire Street between 20th and 23rd streets; Streets temporarily closed 7am - 5pm
- Friday, June 13: Asphalt repaving on Hampshire Street between 23rd and 24th streets; 23rd Street between Hampshire Street and Potrero Avenue; and 26th Street between Hampshire and Bryant streets; Streets temporarily closed 7am - 5pm
Week of June 16
- Construct curb ramps - Intersection of Bryant and Cesar Chavez streets
- Brick cistern ring installation - Intersection of 26th and Bryant streets