Active Alerts

If you are experiencing a water, power, or sewer emergency or service problem call our 24-hour hotline at 3-1-1 or (415) 701-2311 from outside SF or log on at sf311.org. Learn more or review active service alerts.

Hampshire and York Streets Utility Upgrade Project

Overview

Critical upgrades to our aging water and sewer infrastructure are planned for:

  • Hampshire and York streets between Mariposa and Cesar Chavez streets
  • Bryant Street between Precita Avenue and 26th Street
  • 23rd and 25th streets between Hampshire Street and Potrero Avenue
  • 26th Street between Bryant and Hampshire streets
  • Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp 

This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration. 


Construction Look Ahead

Week of May 5

  • Curb ramp installation - Intersections of Bryant and Cesar Chavez streets, and 18th and Hampshire streets
  • Pipeline connections - Hampshire Street between 18th and Mariposa streets

Week of May 12

  • T-trench and street base concrete restoration - Hampshire Street between 18th and Mariposa streets
  • Curb ramp installation - Intersection of 18th and Hampshire streets

Week of May 19

  • Curb ramp installation - Intersection of 18th and Hampshire streets

 

Map showing where construction will take place for the Hampshire and York streets project

  • Construction Start: July 2023
  • Construction End: December 2025
  • Project Phase: Construction