Sewer Upgrades: Renewal & Replacement Program

For Today, Tomorrow and Decades to Come

We strive to minimize disruption and to provide our neighbors with timely and accurate status updates. Public notices have been mailed to the work areas listed.
If you are experiencing a water, power, or sewer emergency service issue call our 24-hour hotline at 3-1-1 or log on at sf311.org.

Streets listed show day work, see the planned night work webpage if you've received a Night Notice.

A reliable system requires maintenance. SFPUC-led infrastructure projects partner with many agencies to dig once and work efficiently. However, coordination challenges and/or unforeseen complications (e.g. unstable soil conditions) may result in delays. A pause in work occurs between sewer upgrade inspections and street restoration.

Thank you for your patience as we upgrade our critical infrastructure to be resilient and reliable. For more information, contact us at: ssip@sfwater.org or 888-581-PIPE (7473).

Can't find any information about the work on your street? see Contacts and Resources below.


Sewer Upgrades Status

Construction is listed by Street | Project Number | Supervisorial District Number

Anza Street (22nd Ave. to 23rd Ave.) | WW-729 | D1
Sewer upgrades complete, round-about and road restoration anticipated Aug-Sept.

Arkansas Street (16th St to Mariposa.) | WW-727 | D6
Sewer upgrades anticipated to begin July, estimated completion Oct.

Baltimore Street (Cordova St. to Naylor St.) | WW-720 | D11
Sewer upgrades in progress, rocky conditions in trench work restoration. Paving and estimated completion July.

Beach Street (Hyde St. to Columbus Ave.) | WW-709 | D2, D3
Sewer upgrades anticipated to resume Summer 2026.Delayed due to PG&E, water utility conflict and re-design. Estimated duration 5 months.

Bergen Alley (at Hyde St.) | WW-709 | D2
Sewer upgrades anticipated to begin Sept., estimated completion Oct.

Bryant Street (3rd St to Ritch St. to Zoe St.) | WW-730 | D6
Sewer upgrades, pipelining and new manhole anticipated Aug.

Buchanan Street (Marina Blvd to No. Point St.) | WW-727 | D2
Sewer upgrades and inspections complete, estimated road restoration July.

Cedar Street (Polk St to Van Ness Ave.) | WW-727 | D3
Sewer upgrades anticipated to begin July, estimated completion Oct.

Clayton Street (Fulton St. to Grove St.) | WW-727 | D5
Sewer upgrades complete, inspections in progress, final road restoration TBD.

College Avenue (Saint Mary's Aves to Mission St. | WW-729 | D8
Sewer upgrades complete, inspections in-progress, road restoration TBD

Columbus Avenue (Beach St to N. Point St) | WW-709 | D2, D3
Sewer upgrades complete, inspections in-progress, road restoration TBD

Columbus Avenue (North Point St to Bay St) | WW-709 | D2, D3
Anticipated to begin TBD, estimated duration 5 months, estimated completion TBD.

Cumberland Street (Dolores to Guerrero streets) | WW-730 | D8
Sewer upgrades in-progress, anticipated completion Sept.

Excelsior Avenue (Madrid St. to Lisbon St.) | WW-730 | D11
Sewer upgrades complete, inspections in progress, anticipated road restoration July.

Federal Street (at Delancy St.| South End Historical District) | WW-730 | D6
Sewer upgrades in progress, estimated duration 1 month.

Fillmore Street (Marina Blvd to Jefferson St.) | WW-727 | D2
Sewer upgrades complete, inspections in progress, estimated road restoration July.

Fillmore Street (Union St to Pixley St.) | WW-727 | D2
Sewer upgrades in progress, estimated completion Oct.

Francisco Street (Broderick St. to Divisadero St. | WW-729 | D2
Sewer upgrades in progress, pending lining and road restoration, estimated completion July.

Gates Street (Ogden Ave. to Tompkins Ave.) | WW-720 | D9
Pending due to water service upgrades, street partially restored till sewer upgrades continue. TBD.

Holladay Ave (Costa St. to Rutledge St.) | WW-720 | D9
Sewer upgrades in-progress. Estimated completion July.

Jones Street (at Northpoint St.) | WW-709 | D3
Sewer upgrades in-progress. Delayed due to poor soil conditions. Estimated completion Sept.

Kansas Street (22nd St. to 20th St/Hillside St.) | WW-720 | D6
Water project in-progress. Sewer upgrades pending re-design, anticipated to begin Aug.

Kansas Street (24th St to 25th St) | WW-730 | D10
Sewer upgrades in-progress, anticipated completion Aug.

Larkin Street (Beach St. to Northpoint St. and Northpoint to Bay streets) | WW-709 | D2
Sewer upgrades complete, road restoration pending.

Mangels Street (Detroit St. to Congo St.) | WW-720 | D7
Sewer upgrades in progress, estimated completion early July.

Marina Boulevard & Yacht Road | WW-709 | D2
Delayed due to poor soil conditions. Sewer upgrades anticipated to resume TBD.

Marina Boulevard (Baker St. to Lyon St.) | WW-709 | D2
Delayed due to poor soil conditions. Anticipated to resume TBD, estimated duration 2 months.

Northpoint St. (Columbus Ave to Jones St) | WW-709 | D3
Sewer upgrades complete, inspections in-progress, street restoration TBD. 

Northpoint St. (Hyde St. to Leavenworth St.) | WW-709 | D2
Sewer upgrades anticipated Aug. Delayed due to poor soil conditions.

Pennsylvania Street (18th St. to Mariposa St.) | WW-729 | D10
Sewer upgrades complete, inspections in-progress, anticipated road restoration July.

Pixley Street (Webster St. to Buchanan St.) | WW-720 | D2
Sewer upgrades complete, design pause - lateral work pending, road restoration TBD.

Prague Street (Russia Ave. to Persia Ave.) | WW-720 | D11
Sewer upgrades in progress, estimated completion Aug.

Prentiss Street (Ogden to Tomkins avenues) | WW-730 | D9
Sewer upgrades in-progress, anticipated completion and road restoration late July.

San Jose Street (Juri St to 26th St) | WW-730 | D8
Sewer upgrades anticipated summer 2026

Scott Street (Pacific St. to Broadway St.) | WW-729 | D2
Delayed due to AT&T and PG&E coordination, anticipated to begin Aug, estimated duration 2 months.

Yacht Road (Marina Blvd. to end) | WW-709 | D2
Sewer upgrades anticipated to occur Aug-Oct 2026 and Apr-May 2027.