Sewer Upgrades: Renewal & Replacement Program
For Today, Tomorrow and Decades to Come
We strive to minimize disruption and to provide our neighbors with timely and accurate status updates. Public notices have been mailed to the work areas listed.
If you are experiencing a water, power, or sewer emergency service issue call our 24-hour hotline at 3-1-1 or log on at sf311.org.
A reliable system requires maintenance. SFPUC-led infrastructure projects partner with many agencies to "dig once" and work efficiently. However, coordination challenges and/or unforeseen complications (e.g. unstable soil conditions) may result in delays. A pause in work occurs between sewer upgrade inspections and street restoration.
Thank you for your patience as we upgrade our critical infrastructure to be resilient and reliable. For more information, contact us at: ssip@sfwater.org or 415-554-3233.
Can't find any information about the work on your street? see Contacts and Resources below.
Construction is listed by Street | Project Number | Supervisorial District Number
5th Avenue (Judah to Irving streets) | WW-725 | D7
Sewer upgrades complete, infrastructure maintenance, inspections in progress.
6th Avenue (Geary Blvd. to Anza St.) | WW-725 | D1
Sewer upgrades complete, road restoration complete, inspections in progress.
14th Avenue (Balboa to Anza streets) | WW-725 | D1
Sewer upgrades day pipe-lining anticipated (2) Saturdays July 24 & 25, 8 a.m. - 4 p.m.
16th Avenue (Lincoln Way to Irving St) | WW-725 | D7
Sewer upgrades day pipe-lining anticipated (2) Saturdays July 24 & 25, 8 a.m. - 4 p.m.
20th Street (Mission to San Carlos streets) | WW-729 | D9
Sewer upgrades anticipated to begin August, estimated duration 1 month.
30th Street (Noe to Harper streets.) | WWW-725 | D8
Sewer upgrades day pipe-lining anticipated Saturday July 26, 8 a.m. - 4 p.m.
38th Avenue (Cabrillo to Balboa streets.) | WWW-726 | D1
Sewer upgrades complete, road restoration complete, inspections pending, estimated completion July.
Alameda Street (Harrison St to Treat Ave | WW-725 | D6
Sewer upgrades day pipe-lining anticipated Saturday July 19, 8 a.m. - 4 p.m.
Bay Street (Hyde to Larkin streets) | WW-709 | D2
Delayed due to poor soil conditions. Sewer upgrades complete, road restoration pending, estimated to be completed August.
Bay Street (Leavenworth to Hyde streets) | WW-709 | D2
Delayed due to poor soil conditions. Crews to complete Hyde to Larkin streets, then will return to this section of Bay St. Project is estimated to be completed August.
Buchanan Street (Sutter to Bush streets.) | WWW-725 | D5
Sewer upgrades complete, road restoration pending, estimated completion August.
Cabrillo Street (La Playa St. to 47th Ave.) | WWW-726 | D1
Sewer upgrades complete, road restoration and inspections pending, estimated completion August.
Cabrillo Street (46th to 47th avenues) | WWW-726 | D1
Sewer upgrades in progress, road restoration and inspections pending, estimated completion August.
California Street (Walnut to Laurel streets) | WW-725 | D2
Sewer upgrades complete, road restoration complete, inspections in progress.
Cesar Chavez Street (Noe to Sanchez streets) | WW-720 | D8
Sewer upgrades anticipated to begin August, estimated duration 3 months.
Chestnut Street (Columbus Ave. to Mason St.) | WW-725 | D1
Sewer upgrades anticipated to begin TBD
Columbus Avenue (Beach to North Point streets) | WW-709 | D2
Sewer upgrades anticipated to begin TBD, estimated duration 4 months.
Dolores Street (San Jose Ave. to 30th St.) | WWW-725 | D8
Sewer upgrades in progress, estimated duration 1.5 months.
Jackson Street (Gough to Octavia streets) | WW-725 | D2
Sewer upgrades complete, road restoration complete, inspections in progress.
Marina Boulevard (Webster to Beach streets) | WW-725 | D2
Sewer upgrades in progress. Pipe-lining day work, Saturday July 19, 8 a.m. - 4 p.m.
Marina Boulevard & Yacht Road | WW-709 | D2
Delayed due to poor soil conditions. Sewer upgrades 68% Complete. Anticipated to resume late September, estimated duration 2 months.
Noe Street & 30th Street intersection | WW-725 | D8
Sewer upgrades day pipe-lining anticipated Saturday July 26, 8 a.m. - 4 p.m.
Oakwood Street (18th to 19th streets) | WW-729 | D8
Sewer upgrades anticipated to begin July, estimated duration 1 month.
Park Street (Leese St. to Holly Park Cir.) | WW-725 | D9
Sewer upgrades complete, misc. items, inspections and road restoration pending.
Pixley Street (Webster to Buchanan streets) | WW-720 | D2
Sewer upgrades complete, road restoration and inspections pending.
Post Street (Franklin St. to Van Ness Ave.) | WW-725 | D2
Sewer upgrades day pipe-lining anticipated Saturday Aug 9, 8 a.m. - 4 p.m.
Starr King Way & Franklin Street | WW-725 | D2
Sewer upgrades complete, road restoration and inspections pending.
Winston Drive Easement (Broadmoor Dr to Junipero Sera Blvd | WW-725 | D7
Sewer upgrades day pipe-lining anticipated (2) Saturdays July 19 & 26, 8 a.m. - 4 p.m.
-
What to Expect During Construction
PARKING: Street parking will be restricted in the project area during construction hours. “No-parking” signs will be posted 72 hours in advance. Please see posted signs for exact workdays, hours, locations, as they may vary depending on construction task.
SEWER AND WATER SERVICES in the area will NOT be interrupted during construction.
TRAFFIC: Street closures in the project area will be necessary to ensure safety of workers and the public. Advance notice and detour signage will be provided.
ACCESS: Follow posted signage on site. Businesses and residents in the work zone may experience limited or no access to driveways and garages when excavation work is in progress adjacent to your driveway. Attempts will be made to advise residents to move vehicles in and out at particular hours to ensure work site safety for crew and the public. If feasible, crews will facilitate access to driveways and entrances during construction.
NOISE: Neighbors may hear construction noise periodically. Noisy work will be conducted in compliance with the San Francisco Noise Ordinance.
ODORS: If necessary, odor control measures will be in place during construction.
CURED-IN-PLACE-PIPE (CIPP): CIPP is a trenchless sewer rehabilitation method that requires insertion of a synthetic pipe liner into the sewer pipe through existing manholes or similar access points. This process uses a resin-saturated felt tube to line the inside of the existing pipe. Vapor and odors can be released during the resin curing process, which includes heating, curing and cool down. Each segment typically requires two to three days of continuous 24/7 to complete but can vary depending on the size of the pipe.
-
What You Can Do
SEWER LATERALS
You can reduce the risk of sewer backups.
Keep your upper and lower sewer laterals in good condition.How to Protect your Property and Environment?
Never let fats, oils or grease go down the drain; compost it instead. Dumping grease down the drain can clog the sewer pipes, result in back-ups or overflows onto your property or streets, foul odors, and costly damage to sewer infrastructure.Remember that your toilet is an only-human-waste-and-toilet-paper-zone. Nothing, except the 3 P’s (pee, poop and toilet paper), go down the drains.
Upper Lateral Responsibility:
The upper sewer lateral is an extension of your home, even if you can’t see it, which means you're fully responsible for it. That’s why we encourage property owners to inspect and keep their lateral clear of trash, grease and other materials (anything except human waste or toilet paper) that can clog and damage pipes. Property owners are responsible for maintenance, including clearing and jetting the pipe to keep the pipe clear and in good working order.If the pipe is found in bad condition, property owners must also repair and replace according to latest San Francisco Plumbing Codes. Check out the Sewer Lateral Standards for property owners, contractors or developers.
Lower Lateral Responsibility:
You are responsible for maintaining it, including clearing and jetting the pipe to keep it clear and in good working order by regularly clearing it or inspecting it using Closed Circuit Television (CCTV) to identify any defects. And of course, by not putting trash, grease, cooking oil, or other materials down household drains.Please notify lower lateral issues and any potential need to repair or replace it to the San Francisco Public Utilities Commission (SFPUC) by calling 3-1-1 or submitting a service request online at sf311.org.
https://www.sfpuc.gov/learning/emergency-preparedness/sewer-laterals
ODORS during Cured-In-Place-Pipe (sewer lining process)
If weather permits, close your windows during the work. To help reduce odors that may travel through the lateral pipes, run water in all sinks and drains to make sure p-traps are filled (p-traps are the “u” shape portion of drain pipes). Drains can also be covered with a wet towel.
This sewer rehabilitation method uses resin to provide the structural rigidity needed to
rehabilitate the pipe. These resins can give off an odor during the curing process. These odors typically
dissipate fairly quickly after the process is completed. We continue to evaluate industry best-practices and
new technologies, including non-styrene-based resins to further reduce the impact of our work.https://www.sfpuc.gov/sites/default/files/documents/CIPL_Information_Factsheet_2025.pdf
-
Contacts and Resources
SFPUC Sewer Communications 415-554-3233 or ssip@sfwater.org
Emergencies
If you are experiencing a water, power, or sewer emergency or service problem call our 24-hour hotline at 3-1-1 or log on at sf311.org.
Can't find any information about the work on your street?
- The project could be a joint project co-managed with other City agencies. For SFMTA led projects, please visit sfmta.com/projects. For SFDPW projects, please visit sfpublicworks.org/projects.
- It is possible the work is in response to an emergency water, water main breaks, or sewer line repair.
- It could be a short-term project of less than a 15 days duration.
- The work may be sewer inspection and cleaning or sewer repair.
- SFPUC posts a schedule of planned night work.
- The work may be a P, G & E Utility project.
- The work may be private development construction.
- The parking restrictions posted on A-frames will show the name of the contractor and contact info.